ANALISIS OPTIMALISASI WAKTU DAN BIAYA DENGAN APLIKASI MICROSOFT PROJECT PADA PROYEK PENGGANTIAN JEMBATAN SUNGAI BERANGAS DENGAN PENAMBAHAN JAM KERJA

Tamimi, Hairul (2021) ANALISIS OPTIMALISASI WAKTU DAN BIAYA DENGAN APLIKASI MICROSOFT PROJECT PADA PROYEK PENGGANTIAN JEMBATAN SUNGAI BERANGAS DENGAN PENAMBAHAN JAM KERJA. Diploma thesis, Universitas Islam Kalimantan MAB.

[img] Text
ARTIKEL ILMIAH TAMIMI.pdf

Download (712kB)

Abstract

Dalam mempercepat penyelesaisan proyek dilakukan dengan beberapa kebijakan, salah satunya adalah menambah jam kerja (lembur). Pada penelitian ini metode yang dipakai adalah Microsoft Project didapat durasi proyek setelah percepatan. Setelah itu ditentukan durasi proyek yang optimum dan biayanya. Dari alternatif percepatan dengan penambahan jam kerja (lembur) 1 jam, 2 jam, dan 3 jam setelah dilakukan crash program diperoleh masing-masing total durasi proyek setelah dipercepat dan total cost. Bandingkan semua alternatif tersebut, sehingga dapat dilihat mana yang lebih efektif. Dari hasil penelitian dan pembahasan diperoleh sebagai berikut, 1. Percepatan durasi proyek menyebabkan pengurangan durasi proyek namun berakibat pada penambahan biaya proyek. 2. Percepatan durasi proyek menggunakan program Microsoft project 2007 dengan alternatif penambahan jam kerja (lembur) memberikan hasil output yaitu sebagai berikut : Waktu optimum yang diperoleh dari percepatan durasi untuk penambahan 1 jam yaitu 251 hari. 1). Waktu optimum yang diperoleh dari percepatan durasi untuk penambahan 2 jam yaitu 253 hari. 2). Waktu optimum yang diperoleh dari percepatan durasi untuk penambahan 3 jam yaitu 249 hari. 3). Waktu optimum yang diperoleh dari percepatan durasi untuk penambahan 3 jam yaitu 249 hari. penambahan biaya akibat percepatan waktu pelaksanaan proyek : 1). Untuk penambahan 1 jam kerja lembur dari Rp 24.894.380.000 menjadi Rp25.233.260.787 . 2). Untuk penambahan 2 jam kerja lembur dari Rp 24.894.380.000 menjadi Rp25.513.933.466 . 3). Untuk penambahan 3 jam kerja lembur dari Rp 24.894.380.000 menjadi Rp 25.514.586.040. In accelerating the completion of a project is usually done with some policies, one of which is to add hours of work (overtime). In this study the method used was with Microsoft Project obtained the duration of the project after acceleration. Once that is determined the duration of the project is optimal and costs. From alternative acceleration with the addition of working hours (overtime) 1 hour, 2 hours, and 3 hours after the crash of the program obtained each of the total duration of the project after accelerated and total cost. Compare all these alternatives, so it can be seen which is more effective. From the results of research and discussion is obtained as follows, 1. Project duration acceleration causes reduced project duration but results in the addition of project costs. 2. Acceleration of project duration using Microsoft Project 2007 program with alternative addition of working hours (overtime) gives output result which is as follows: Optimum time gained from the acceleration duration for 1 hour increments are 251 days. 1). The optimum time gained from the acceleration duration for 2 hours increments is 253 days. 2). The optimum time gained from the acceleration duration for an addition of 3 hours is 249 days. 3). The optimum time gained from the acceleration of the duration for the addition of 3 hours is 249 days. Additional costs due to the acceleration of project execution Time: 1). For the addition of 1 hour of overtime work from Rp 24,894,380,000 to Rp 25.233.260.787. 2). For the addition of 2 hours of overtime work from Rp 24,894,380,000 to Rp 25.513.933.466. 3). For the addition of 3 hours of overtime work from Rp 24,894,380,000 to Rp 25,514,586,040.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Pengendalian Waktu dan Biaya, Microsoft project, Perbandingan. time and cost control, Microsoft project, Comparison.
Subjects: Q Science > Q Science (General)
Q Science > QA Mathematics
Q Science > QC Physics
Q Science > QE Geology
T Technology > TA Engineering (General). Civil engineering (General)
Depositing User: Hairul Tamimi
Date Deposited: 07 May 2021 02:09
Last Modified: 07 May 2021 02:09
URI: http://eprints.uniska-bjm.ac.id/id/eprint/5160

Actions (login required)

View Item View Item