ANALISIS WAKTU DAN PRODUKTIVITAS ALAT BERAT PADA PEMBUATAN BANGUNAN PINTU AIR DI TAMBANG SENAKIN, KABUPATEN KOTABARU

PRIYANTO, BUDI (2021) ANALISIS WAKTU DAN PRODUKTIVITAS ALAT BERAT PADA PEMBUATAN BANGUNAN PINTU AIR DI TAMBANG SENAKIN, KABUPATEN KOTABARU. Diploma thesis, Universitas Islam Kalimantan MAB.

[img] Text
ARTIKEL ILMIAH ANALISIS WAKTU & PRODUKTIVITAS ALAT BERAT (BUDI PRIYANTO 16640112).pdf

Download (375kB)

Abstract

Alat berat merupakan satu kesatuan yang tidak dapat dipisahkan dalam pekerjaan pembangunan sarana dan prasarana. Alat berat lebih menguntungkan jika dibandingkan dengan menggunakan alat manual karena dapat menyelesaikan pekerjaan pembangunan lebih cepat, sehingga waktu pelaksanaan pekerjaan dapat tercapai dengan optimal. Kelancaran proyek sangat bergantung pada peralatan yang digunakan seperti pemilihan alat berat, kebutuhan alat di proyek harus sesuai dengan fungsi alat masing-masing. Hal ini diperlukan agar alat tersebut dapat bekerja secara optimum sehingga pekerjaan dapat diselesaikan tepat waktu dengan biaya sehemat mungkin. Dalam penelitian ini dilakukan analisis produktivitas alat berat pada pekerjaan galian tanah pada Pembuatan Bangunan Pintu Air di Tambang Senakin, Kabupaten Kotabaru. Analisis perhitungan produktivitas alat berat dalam penelitian ini menggunakan persamaan-persamaan dari Rochmanhadi (1983) dan Komatsu (1997). Sedangkan alat berat yang dianalisis dalam pekerjaan galian tanah adalah excavator dan dump truck. Untuk excavator menggunakan merk dan jenis: Komatsu PC200-8, kapasitas bucket: 1 m3 dan tahun pembuatan: 2015, sedangkan dump truck menggunakan merk dan jenis: Mitsubishi 120 Ps, kapasitas muatan: 9 m3 dan tahun pembuatan: 2006. Berdasarkan hasil analisis diperoleh waktu pelaksanaan proyek pekerjaan galian tanah berdasarkan jumlah peralatan yang tersedia adalah waktu penggalian menggunakan excavator selama 84,78 jam dan waktu angkut menggunakan dump truck selama 668,55 jam. Sehingga diperoleh produktivitas kerja masing-masing alat berat yang digunakan berdasarkan pendekatan perhitungan secara teoritis adalah untuk alat excavator sebesar 357 m3/jam dan untuk alat dump truck sebesar 53,44 m3/jam. Heavy equipment is an inseparable unit in the construction of facilities and infrastructure. Heavy equipment is more profitable when compared to using manual tools because it can complete construction work faster, so that the time to carry out work can be achieved optimally. The smooth running of the project really depends on the equipment used, such as the selection of heavy equipment, the needs of the tools in the project must be in accordance with the function of each tool. This is necessary so that the tool can work optimally so that the work can be completed on time at the lowest possible cost. In this study, an analysis of the productivity of heavy equipment was carried out on the excavation work of the Water Gate Building at the Senakin Mine, Kotabaru Regency. The analysis of heavy equipment productivity calculations in this study uses equations from Rochmanhadi (1983) and Komatsu (1997). Meanwhile, the heavy equipment analyzed in the excavation work are excavators and dump trucks. The excavator uses the brand and type: Komatsu PC200-8, bucket capacity: 1 m3 and year of manufacture: 2015, while the dump truck uses the brand and type: Mitsubishi 120 Ps, load capacity: 9 m3 and year of manufacture: 2006. Based on the results of the analysis, it is obtained that the time for the earth excavation project implementation based on the number of equipment available is the excavation time using an excavator for 84.78 hours and the transport time using a dump truck for 668.55 hours. In order to obtain the work productivity of each heavy equipment used based on the theoretical calculation approach, the excavator is 357 m3 / hour and the dump truck is 53.44 m3 / hour.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Waktu Penggunaan Alat Berat, Produktivitas Alat Berat, Tambang Senakin. Time of Use of Heavy Equipment, Productivity of Heavy Equipment, Senakin Mine.
Subjects: Q Science > Q Science (General)
Depositing User: Budi Priyanto
Date Deposited: 25 Jun 2021 01:20
Last Modified: 25 Jun 2021 01:20
URI: http://eprints.uniska-bjm.ac.id/id/eprint/5853

Actions (login required)

View Item View Item