ANALISIS TIME COST TRADE OFF (TCTO) PADA PEKERJAAN MENARA DETAIL ENGINEERING DESIGN (DED) LANJUTAN MAKAM SYECH MUHAMMAD ARSYAD AL BANJARI KELAMPAYAN KABUPATEN BANJAR

ARAFAT, M REZKI (2021) ANALISIS TIME COST TRADE OFF (TCTO) PADA PEKERJAAN MENARA DETAIL ENGINEERING DESIGN (DED) LANJUTAN MAKAM SYECH MUHAMMAD ARSYAD AL BANJARI KELAMPAYAN KABUPATEN BANJAR. Diploma thesis, Universitas Islam Kalimantan MAB.

[img] Text
ARTIKEL SKRIPSI.pdf

Download (121kB)

Abstract

Kalimantan Selatan memiliki banyak destinasi wisata religi seperti masjid atau surau tua dengan arsitekturnya yang khas hingga makam-makam ulama. Kabupaten Banjar misalnya, memiliki beberapa destinasi wisata religi. Di antaranya yang paling terkenal adalah Makam Syekh Muhammad Arsyad Al Banjari. Sosok Syekh Muhammad Arsyad Al Banjari memang dikenal sebagai seorang ulama yang alim dan saleh di masanya. Beliau dilahirkan di Desa Lok Gabang, Kabupaten Banjar pada 17 Maret 1710 dan meninggal dunia di Dalam Pagar, Kabupaten Banjar pada 13 Oktober 1812. Makamnya berada di Desa Kalampayan Tengah, Kecamatan Astambul, Martapura, Kabupaten Banjar. Penjadwalan proyek yang dilakukan selama ini pada proyek konstruksi di Kalimantan Selatan Banjarmasin masih jarang sekali menggunakan metode yang telah baku seperti TCTO. Sehingga kerap kali terjadi perbedaan antara rencana kerja dengan realisasi pekerjaan, yang pada akhirnya menyebabkan keterlambatan dalam penyelesaian proyek. Sehingga perlu kiranya mengkaji TCTO yang memiliki kelebihan dalam penjadwalan proyek sekaligus metode percepatan proyek, jika di tengah jalan diketahui proyek mengalami keterlambatan dari rencana kerja awal. Berdasarkan hasil analisis menggunakan metode Time Cost Trade Off diperoleh waktu penyelesaian proyek yang semula 240 hari berubah menjadi 210 hari sehingga terdapat selisih waktu 30 hari dari jadwal normal proyek, dan tambahan biaya dimana pada kondisi biaya normal proyek adalah sebesar Rp 13.174.676.934,98,- dan total biaya tambahan pekerjaan proyek setelah percepatan dengan menggunakan metode TCTO adalah sebesar Rp 314.446.667,43,- sehingga mengurangi keuntungan proyek sebesar 2,3 % dari nilai kontrak atau 15 % dari keuntungan. Kata Kunci : Analisis Time Cost Trade Off (TCTO), Cost Slope Waktu dan Biaya. South Kalimantan has many religious tourism destinations such as mosques or old surau with distinctive architecture to the tombs of scholars. Banjar Regency, for example, has several religious tourism destinations. Among the most famous is the Tomb of Sheikh Muhammad Arsyad Al Banjari. The figure of Sheikh Muhammad Arsyad Al Banjari was indeed known as a pious and pious scholar in his time. He was born in Lok Gabang Village, Banjar Regency on March 17, 1710 and died in Dalam Pagar, Banjar Regency on October 13, 1812. His grave was in Kalampayan Tengah Village, Astambul District, Martapura, Banjar Regency Project scheduling carried out so far on the construction project in South Kalimantan Banjarmasin still rarely uses standard methods such as TCTO. So that there are often differences between work plans and work realization, which in turn causes delays in project completion. So it is necessary to review the TCTO which has advantages in project scheduling as well as the project acceleration method, if in the middle of the road it is known that the project is experiencing delays from the initial work plan. Based on the results of the analysis using the Time Cost Trade Off method, the completion time of the project which was originally 240 days changed to 210 days so that there is a difference of 30 days from the project's normal schedule, and additional costs where the project's normal cost is IDR 13,174,676,934.98, - and the total additional cost of project work after acceleration using the TCTO method is Rp. 314,446,667.43,- thus reducing the project profit by 2.3% of the contract value or 15% of the profit. Keywords: Time Cost Trade Off (TCTO) Analysis, Cost Slope Time and Cost

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Analisis Time Cost Trade Off (TCTO), Cost Slope Waktu dan Biaya.
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Depositing User: M. Rezki Arafat
Date Deposited: 23 Jun 2021 03:38
Last Modified: 23 Jun 2021 03:38
URI: http://eprints.uniska-bjm.ac.id/id/eprint/5857