PERHITUNGAN PRODUKTIVITAS PEKERJAAN PEMASANGAN DINDING BATA RINGAN DENGAN METODE TIME STUDY PADA PROYEK PEMBANGUNAN RUANG KANTOR SEKOLAH MENENGAH ATAS NEGERI 5 BANJARMASIN

Nordiansyah, Muhammad (2021) PERHITUNGAN PRODUKTIVITAS PEKERJAAN PEMASANGAN DINDING BATA RINGAN DENGAN METODE TIME STUDY PADA PROYEK PEMBANGUNAN RUANG KANTOR SEKOLAH MENENGAH ATAS NEGERI 5 BANJARMASIN. Diploma thesis, Universitas Islam Kalimantan MAB.

[img] Text
17640040-Muhammad Nordiansyah-Artikel.pdf

Download (688kB)

Abstract

Dalam proyek konstruksi, produktivitas merupakan hal penting terhadap kesuksesan proyek tersebut. Proyek Pembangunan Ruang Kantor Sekolah Menengah Atas Negeri (SMAN) 5 Banjarmasin. Sebagai perbandingan dalam penelitian tentang produktivitas pekerja ini adalah SNI 2016. Produktivitas pekerjaan yang diteliti adalah pekerjaan pasangan dinding bata ringan ringan. produktivitas pekerja konstruksi gedung terutama pekerjaan pasangan dinding bata ringan pada waktu pagi dan siang hari apakah ada perbedaan produktivitas pekerja konstruksi gedung terutama pekerjaan pasangan dinding bata ringan pada pagi dan siang hari. Metode yang saya gunakan untuk penelitian ini adalah Time study dengan pengumpulan data berdasarkan waktu yang dibutuhkan untuk menyelesaikan suatu pekerjaan. Time study meliputi Timing, Rating, Standar time, Standard Rating, Observed Time, Observed Rating, Basic Time. Hasil perhitungan nilai rata – rata produktivitas pekerjaan pemasangan bata ringan dan pekerjaan pelesteran pada pagi hari 0,2374 m2/orang per jam siang hari 0,2222 m2/orang per jam sedangkan pekerjaan pelesteran rata – rata produktivitasnya juga mengalami peningkatan di pagi hari 0,3442 m2/orang per jam dibandingkan siang hari 0,3306 m2/orang per jam. In a construction project, productivity is important to the success of the project. State High School Office Office Building Project (SMAN) 5 Banjarmasin. In comparison in this study on worker productivity is SNI 2016. The productivity of the work studied was the work of a light brick wall pair. The productivity of building construction workers especially the work of light brick wall pairs in the morning and during the day is there a difference in the productivity of building construction workers, especially the work of light brick wall pairs in the morning and during the day. The method I used for this research is time study with data collection based on the time it takes to complete a job. Time studies include Timing, Rating, Standard time, Standard Rating, Observed Time, Observed Rating, Basic Time. The results of the calculation of the average value - the average productivity of light brick installation work and sterilization work in the morning 0,2374 m2 / person per hour during the day 0,2222 m2 / person per hour while the level of sterilization work - the average productivity also increased in the morning 0,3442 m2 / person per hour compared to noon 0,3306 m2 / person per hour.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Produktivitas, Time Study, Dinding Bata Ringan Productivity, Time Study, Light Brick Wall
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Depositing User: Muhammad Nordiansyah
Date Deposited: 13 Oct 2021 03:53
Last Modified: 13 Oct 2021 03:53
URI: http://eprints.uniska-bjm.ac.id/id/eprint/8418