ANALISIS PERCEPATAN PROYEK MENGGUNAKAN METODE CRASH PROGRAM TERHADAP WAKTU DAN BIAYA PADA PEMBANGUNAN GEDUNG SERBAGUNA KECAMATAN KURIPAN

Wahyudi, Wahyudi (2022) ANALISIS PERCEPATAN PROYEK MENGGUNAKAN METODE CRASH PROGRAM TERHADAP WAKTU DAN BIAYA PADA PEMBANGUNAN GEDUNG SERBAGUNA KECAMATAN KURIPAN. Diploma thesis, Universitas Islam Kalimantan MAB.

[img] Text
Artikel Kuripan.pdf

Download (397kB)

Abstract

Pada proyek Pembangunan Gedung Serbaguna Kecamatan Kuripan ini terdapat keterlambatan pada minggu ke 13 sehingga ada penundaan pekerjaan yang mengalami deviasi sebesar -6,06 %. Skripsi ini upaya mencari solusi dari masalah percepatan penyelesaian proyek pada pelaksanaan proyek Pembangunan Gedung Serbaguna Kecamatan Kuripan menggunakan metode percepatan (crashing). Keterlambatan proyek dapat di antisipasi dengan melakukan percepatan (crashing) dalam pelaksanaannya, namun harus tetap memperhatikan faktor biaya. Pertambahan biaya yang dikeluarkan diharapkan seminimum mungkin dan tetap memperhatikan standar mutu. Hasil dari Analisis yang didapat dengan menggunakan metode crashing program pada pembangunan gedung serbaguna kecamatan Kuripan dengan penambahan jam lembur 3 jam, ini dapat diselesaikan dalam waktu 164 hari. Dan untuk jam lembur 2 jam dapat diselesaikan dalam waktu 167 hari, sementara untuk jam lembur 1 jam dapat diselesaikan dalam waktu 172 hari. Dengan waktu penyelesaian normal proyek yaitu 180 hari, biaya yang dibutuhkan adalah sebesar Rp. 1,550,520,000.00,- Dengan menambah 3 jam penambahan jam kerja lembur dengan biaya total proyek menjadi Rp. 1.436.429.311,86, Dengan menambah 2 jam penambahan jam kerja lembur sehingga total biaya proyek menjadi Rp. 1.419.012.590,92, sedangkan Dengan menambah 1 jam penambahan jam kerja lembur total biaya proyek menjadi Rp. 1.402.627.443,87. Perbandingan biaya dan waktu proyek normal dan dipercepat untuk percepatan dengan penambahan jam lembur 3 jam untuk durasi selisih 16 hari dari durasi normal. Dan untuk biaya tambahan sebesar Rp.167,822,084.24. dengan penambahan jam lembur 2 jam untuk durasi selisih 13 hari dari durasi normal dengan biaya tambahan sebesar Rp.150,405,363.30. Untuk penambahan jam lembur 1 jam untuk durasi selisih 8 hari dari durasi normal dengan biaya tambahan sebesar Rp.134.020.216,25.. Solusi untuk percepatan pada proyek Pembangunan Gedung Serbaguna Kecamatan Kuripan adalah dengan cara menambah jam lembur 3 jam kerja, karena dengan melakukan alternatif tersebut keterlambatan di minggu ke 13 tersebut dengan deviasi -6,19 % bisa diatasi dengan percepantan waktu 18 hari dengan biaya tambahan sebesar Rp. 160.143.390,04,- dengan cost slope Rp.10.488.880,26.- In the Kuripan District Multipurpose Building Construction project, there was a delay in the 13th week so that there was a delay in work which experienced a deviation of -6.06%. This thesis attempts to find a solution to the problem of accelerating project completion in the implementation of the Kuripan District Multipurpose Building project using the crashing method. Project delays can be anticipated by speeding up (crashing) in its implementation, but must still pay attention to the cost factor. The additional costs incurred are expected to be kept to a minimum and still pay attention to quality standards. The results of the analysis obtained using the crashing program method on the construction of the Kuripan sub-district multipurpose building with the addition of 3 hours of overtime, this can be completed within 164 days. And 2 hours of overtime can be completed in 167 days, while 1 hour of overtime can be completed in 172 days. With a normal project completion time of 180 days, the required cost is Rp. 1,550,520,000.00,- By adding 3 additional hours of overtime work, the total project cost becomes Rp. 1,436,429,311.86, By adding 2 additional hours of overtime work so that the total project cost becomes Rp. 1,419,012,590.92, while by adding an additional hour of overtime the total project cost becomes Rp. 1,402,627,443.87. Comparison of normal and accelerated project costs and time for acceleration with the addition of 3 hours of overtime for the duration of the 16 day difference from the normal duration. And for an additional fee of Rp.167,822,084.24. with the addition of 2 hours of overtime for a duration of 13 days difference from the normal duration with an additional cost of Rp. 150,405,363.30. For the addition of 1 hour of overtime for a duration of 8 days difference from the normal duration with an additional cost of Rp. 134,020,216,25 .. The solution for the acceleration of the Multipurpose Building Development project in Kuripan District is to add 3 hours of overtime work, because by doing the alternative is the delay in the 13th week with a deviation of -6.19% can be overcome by accelerating the time of 18 days with an additional cost of Rp. 160,143,390.04, - with a cost slope of Rp. 10,488,880,26.-

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Analisis, Waktu, Biaya, Crashing Analysis, Time, Cost, Crashing
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Depositing User: Wahyudi
Date Deposited: 17 Feb 2022 04:33
Last Modified: 17 Feb 2022 04:33
URI: http://eprints.uniska-bjm.ac.id/id/eprint/9846

Actions (login required)

View Item View Item